Most AV problems in a finished house were decided months earlier, by people who weren't thinking about AV. Here is how we get in the room before that happens.
There is a version of this story that ends badly, and every architect has seen it. The house is nearly done. The plaster is painted, the millwork is in, the client is happy. Then the AV contractor shows up. Wires get fished through finished walls. Speakers go where they can, not where they should. A beautiful built-in loses a shelf to an equipment rack nobody planned for. The primary suite gets a ceiling speaker directly over the bed, slightly off center, forever.
That is not a technology problem. It is a sequencing problem, and it is completely preventable.
When we should be at the table
Schematic design, ideally. Design development at the latest. Before the walls are drawn to scale, every decision is a line on a drawing. After the walls are framed, every decision is a change order. After the walls are closed, every decision is a compromise with a patch kit.
The first meeting isn't about equipment. It's about how the house is meant to work. Where does the family gather in the morning? Where do the owners entertain? Is there a room that should be completely still, and one that should fill with music? Those are design questions, and they drive almost every technical decision downstream.
What we bring to design development
- Conduit and pathways. The most expensive mistake in AV is not the wrong equipment. It's having no clean way to run it. We lay out conduit and pathways that coordinate with structural, mechanical and electrical, so every wire has a route before framing inspection. Conduit is also the cheapest future-proofing there is. Nobody knows what we'll be plugging in fifteen years from now, but it will need a way in.
- Equipment room size and location. A real Savant or Lutron system needs a rack, and that rack needs space, ventilation and access. Put it in a closet with no airflow and it will run hot for the life of the house. We help size and place it while it's still easy to move.
- Device locations against finish materials. Flush speakers, in-ceiling subwoofers, shade pockets, sensors, cameras and keypads all interact with plaster depth, ceiling height, trim profiles and cabinetry. We give exact locations and rough-in dimensions so the finish trades aren't surprised.
- Lighting control aligned with the lighting designer. If there's a lighting designer on the project, we want to meet them early. Fixture selections and Lutron lighting control have to agree on how things dim, and keypad locations are far cheaper to move on paper.
- Low-voltage rough-in drawings. A drawing set your electrician and general contractor can build from. Not a wish list. A coordinated document.
A typical example
A great room with 22-foot ceilings and a wall of glass. The plan calls for ceiling speakers, because that's where speakers usually go. At that height they sound distant and thin, and they put a row of grilles in a ceiling everyone will stare at. If we're in the room during design development, the better answer is speakers built into the millwork flanking the fireplace, with a subwoofer hidden in the cabinet base. Better sound, nothing to look at.
That option only exists while the millwork is still a drawing. Once it's built, the ceiling wins by default.
What we ask of the design team
Not much. A seat at the early meetings. Floor plans during design development. A working line to the interior designer so we know finishes before we specify devices. And the understanding that our job is to make your work look better, not to compete with it. The best installations are the ones nobody notices, which is an odd thing to be proud of, but here we are.
If you're in planning now
- Bring the integrator in before design development, not after framing.
- Locate the equipment room on the plans with ventilation and access, not "TBD."
- Put conduit everywhere you can't easily get back into later.
- Get the lighting designer, the integrator and the electrician on one call before dimmer locations are set.
Our design, install and maintain process shows where we fit in a build, and the trade partners page is written for architects, designers and builders. The earlier the call, the fewer patches.